Friday, April 30, 2010

Tile

April 30, 2010 -

The floor tile is almost all installed!  Just two more weeks and the wall tile should be done as well as the grout.  Part of the reason it takes so much time is the cure times for the tile adhesive are nearly 3 days.

The second half of May we will install the fixtures, paint the walls and clean it all up!  It looks like we are still on track for our June completion date.

Wednesday, April 14, 2010

Details

April 14, 2010 -

We are nearing the part of the project where the work that is being done will remain visable when the project is done!  It is amazing how much goes into portions of the construction that you can't ever see again once the project is completed.

Since the last update, all of the sheetrock and cement board has been installed, the drywall finishing work has been completed, the walls have been primed, the exhuast duct work has been installed, and the ceiling grid has been installed.  This week the new lights will be installed and the tile installation is starting!