Thursday, March 18, 2010

Sheetrock'n

March 18, 2009 -

One might think today is St. Patrick's Day with all the green walls going up in the new restrooms!  (This photo is taken from the hallway looking toward the Men's restroom door.)


Don't worry - the walls are NOT going to be green when we are done.  They are actually special sheetrock that is designed to be reistant to mold, mildew, and other fun stuff that can grow in wet places. 

Wednesday, March 10, 2010

We've Been Framed!

March 10, 2010 -

The project is moving along very well!  After some delay on the materials delivery the framing is nearly done.  The majority of the space should have framed in walls by the end of the week.



Wednesday, March 3, 2010

The Walls Between Us!

March 3, 2010 -

Differentiation is a very good thing, especially when it comes to restrooms! The Thooft’s have got good start on the framing in the restrooms here at Grace Life Church! Unfortunately, we are still waiting on the 6” steel studs to arrive at True Value. Once they come in (hopefully today) we can finish up the framing and bring the plumbers and electricians in to finish up their parts of the project!

Tuesday, March 2, 2010

Finished Concrete!

March 2, 2010 -

The concrete is done! The space looks like a clean slate. It's ready for some creation now that the destruction and underground infrastructure are installed.



The materials are still not all in at True Value, but there is enough of it on hand to start. If all goes well we will see the framed in walls by the end of the week!

Monday, March 1, 2010

Concrete

March 1, 2010 -

The concrete floor is back in!  Bofferding Construction arrived this morning and poured the concrete in above the areas where the sewer piping was installed last week.  After we give the floor the rest of today to cure, we can start installing the walls.  The Thooft's will be in to start on that tomorrow morning assuming the necessary materials arrive from True Value.