Tuesday, February 23, 2010

Plumbing Rough In

February 23, 2010 -

The demolition is basically done!  The final wall came out yesterday. 

We were pleasantly suprised to see what great condition the existing sewer piping is in!  The plumbers are working today to rough in the sewer plumbing that will run under the concrete.  By early next week we will be puting up the framing for the walls.

Monday, February 15, 2010

Let the Plumbing Begin!

February 5, 2010 -

The MN Dept. of Labor and Industry finally sent back their approval on the plumbing drawings! Waiting on the plans delayed us one week, but now we are back on track! Look for new updates as we finalize permits and start to rough in the plumbing later this week!

Tuesday, February 9, 2010

Phase 1 - Restroom Remodel (Main Entry)

February 1, 2010 -

Grace Life Church has started Phase 1 - Main Entry Restroom Remodeling. The plan is to eliminate the two small main entry restrooms as well as a third small restroom located in the former KinderChurch room and rebuild two large restrooms designed to accommodate the needs of the building users. Our goal is to improve not only the quantity of fixtures, but also to make the restroom facilities much more accessible to all of our building users.

The target completion for this project is June of 2010. Until then please follow the posted signs to alternate restroom facilities through out the building. Additionally, we may need to close the main entry during the demolition and construction project. Please use the MACS entry located directly across from the main entry door. We apologize for the temporary inconvenience as we work on improving the usefulness of this facility for all!

Thank you!